Measures to improve the efficiency of use of underground explosion-proof transformer substations

User Rating:  / 0
PoorBest 

Authors:

G.G. Pivniak, Dr. Sci. (Tech.), Professor, Academician of the National Academy of Sciences of Ukraine, State Higher Educational Institution “National Mining University”, Rector, Dnipropetrovsk, Ukraine

V.T. Zaika, Dr. Sci. (Tech.), Professor, State Higher Educational Institution “National Mining University”, Professor of the Power Supply Systems Department, Dnipropetrovsk, Ukraine

I.M. Lutsenko, State Higher Educational Institution “National Mining University”, Postgraduate Student of the Power Supply Systems Department, Dnipropetrovsk, Ukraine

Abstract:

Purpose. The determination and substantiation of the explosion-proof factory-assembled mobile transformer substations (TS) effective use in a coal mine.

Methodology. The methodology of TS load capacity is based on the transformer insulation deterioration theory and heat processes randomicity complex accounting due to real load data use, variation of environmental factors influence, technical restrictions and standard requirements concerning electric power quality for mining complexes.

Findings. The findings showed that for Western Donbass region coal mines the TS effective use by its load capacity becomes available deu to taking into account the environmental conditions and use 1140 voltage level for mining complexes power supply. The necessity of operating mode monitoring providing with the averaging interval of the 2.5 minute has been proved. These findings allow us to use TS effectively and to replace them for the reason of factual state deterioration before the equipment failure happens. This will provide an opportunity to form the TS park rationally.

Originality. The universal dependence of TS load capacity on environmental factors influence has been established. Conditions for existing power reserves of the explosion-proof TS load capacity extraction have been determined.

Practical value. Received dependences and determined conditions of TS load capacity use will allow assessing factual and forecasting residual life of e substation. It will be useful for optimal TS park forming in coal mine and up-to-date data bases concerning mining complexes operation modes implementation. It will allow developing principles of electric loads calculations for this equipment type and specific exploitation conditions.

References:

1. Система учета и контроля расхода электроэнергии для угольных шахт / [Г.Г. Пивняк, В.В. Ткачев, В.Т. Заика и др.] // Промышл. энергетика.– 1992.– №7.– С. 19–21.
Pivnyak, G.G., Tkachev, V.V., Zaika, V.T., Shishats-kiy, A.A., Nadtochiy, V.V. and Razumnyy, Yu.T. (1992), “System of electric power charge assessment and control for coal mines”, Promyshlennaya energetika, no. 7, pp. 19–21.

2. Півняк Г.Г. Експериментальні дослідження завантаженості електромережного обладнання з метою підвищення ефективності систем підземного електропостачання / Г. Г. Півняк, В. Т. Заїка // Вісник ВТУ. – Вінниця, 1999. – № 6. – С. 26–32.
Pivniak, H.H. and Zaika, V.T. (1999), “Experimental investigations of power network equipment load with the aim of underground power supply system effectiveness increase”, Visnyk VTU, Vinnytsia, no. 6, pp. 26–32.

3. Перегрузочная способность взрывобезопасных трансформаторных подстанций / И.Я. Чернов, В.В. Шилов, В.М. Грушко, В.Л. Кузнецов // Взрывозащищенное электрооборудование: Сб. науч. тр. УкрНИИВЭ. – Донецк: ООО „АИР“, 2011. – C. 42–46.
Chernov, I.Ya, Shilov, V.V., Grushko, V.M. and Kuznetsov, V.L. (2011), “Overload capacity of the explosion-proof transformer substations”, Vzryvozashchishchennoe elektrooborudovanie, UkrNIIVE Scientific collected articles, OOO „AIR“, Donetsk, Ukraine, pp. 42–46.

4. Нагорный М.А. Метод определения нагрузки трансформатора для электроснабжения угледобывающих участков по его фактическому тепловому состоянию / М.А. Нагорный, А.П. Ковалев, Л.И. Колесник // Взрывозащищенное электрооборудование: Сб. науч. тр. УкрНИИВЭ. – Донецк: ООО „Юго-Восток, ЛТД“, 2001. – C. 113–119.
Nagornyy, M.A., Kovalev, A.P. and Kolesnik, L.I. (2001), “Technique of transformer load capacity determination by its factual heat state for mining areas power supply”, Vzryvozaschischennoe elektrooborudovanie, UkrNIIVE Scientific collected articles, OOO “Yugo-Vostok, Ltd.”, Donetsk, Ukraine, pp. 113–119.

5. Трансформаторы рудничные силовые взрывобезопасные. Общие технические условия: ГОСТ 15542–79. – [Действующий с 1982.01.01.], [Электронный ресурс] – Режим доступа: http://www.gosthelp.ru/gost/ gost14588.html.
Transformatory rudnichnye silovye vzryvobezopasnye. Obschie tekhnicheskie usloviya [Flame-Proof Mine Power Transformers. General Specifications], GOST 15542-79, [valid since January 1, 1982], available at: http://www.gosthelp.ru/gost/gost14588.html.

6. Державні санітарні правила та норми „Підприємства вугільної промисловості“: ДСП 3.3.1.095-2002. – [Електронний ресурс] – Режим доступу: http://zakon2. rada.gov.ua/laws/show/z0498-03.
Derzhavni sanitarni pravyla ta normy “Pidpryiemstva vuhilnoi promyslovosti” [State Sanitary Regulations and Norms “Coal Industry Enterprises”], DSP 3.3.1.095-2002, available at: http://zakon2.rada.gov.ua/laws/show/z0498-03

7. Півняк Г.Г. Формування парку вибухозахищених трансформаторних підстанцій вугільних шахт / Г.Г. Півняк, В.Т. Заїка, І.М. Луценко // Уголь Украины. – 2011 – №6. – С. 20–23.
Pivniak, H.H., Zaika, V.T. and Lutsenko, I.M. (2011), “Formation of the reserve of the explosion-proof transformer substations in coal mine”, Uhol Ukrainy, no.6,
pp. 20–23.

8. Заїка В.Т. Способи поглиблення енергоконтролю гірничих машин / В.Т. Заїка, Г.М. Бажін, А.С. Румянцев // Вісник Приазовського державного технічного університету – 2008. – Вип. 18. – С. 27–30.
Zaika, V.T., Bazhin, H.M. and Rumiantsev, A.S. (2008), “Methods of increase of depth of power control of mining machines”, Visnyk Pryazovskoho derzhavnoho tekhnichnoho universytetu, no. 18, pp. 27–30.

9. Савицкий А.В. Основные направления совершенствования комплексной защиты взрывозащищенных трансформаторных подстанций / А.В. Савицкий // Взрывозащищенное электрооборудование: Сб. науч. тр. УкрНИИВЭ. – Донецк: ООО „АИР“, 2009. – C. 94–103.
Savitskiy, A.V. (2009), “Main directions of complex protection upgrading for explosion-proof transformer substations”, Vzryvozaschischennoe elektrooborudovanie, UkrNIIVE Scientific collected articles, OOO “AIR”, Donetsk, Ukraine, pp. 94–103.

Files:
2012_4_pivniak
Date 2013-08-13 Filesize 421.36 KB Download 1658

Visitors

7564948
Today
This Month
All days
4230
87434
7564948

Guest Book

If you have questions, comments or suggestions, you can write them in our "Guest Book"

Registration data

ISSN (print) 2071-2227,
ISSN (online) 2223-2362.
Journal was registered by Ministry of Justice of Ukraine.
Registration number КВ No.17742-6592PR dated April 27, 2011.

Contacts

D.Yavornytskyi ave.,19, pavilion 3, room 24-а, Dnipro, 49005
Tel.: +38 (056) 746 32 79.
e-mail: This email address is being protected from spambots. You need JavaScript enabled to view it.
You are here: Home Archive by issue 2012 Contents No.4 2012 Environmental safety, labour protection Measures to improve the efficiency of use of underground explosion-proof transformer substations